Factors affecting the delay of the construction project of the Phra Khanong Fire and Rescue Station of Bangkok
Keywords:
Delay factors, Building construction projects, Phra Khanong Fire and Rescue Station, Delphi techniqueAbstract
This study aimed to identify, prioritize, and recommend preventive measures for the key factors contributing to delays in the Phra Khanong Fire Station and Rescue Building construction project in Bangkok. Using the Delphi technique, a questionnaire was developed and refined through expert input. Data were collected from 60 individuals involved in the project and analyzed using percentages, means, standard deviations, and risk levels. Results showed that the most significant uncontrollable delay factor was a conflict between the contract design and the Bill of Quantities (BOQ), with a risk level of 14.63. A suggested solution is a thorough review of design and BOQ documents before the bidding process. The most critical partially controllable factor was the contractor’s lack of liquidity and cash flow (risk level 14.30), indicating the need for careful financial planning and understanding of contract terms. For controllable factors, insufficient personnel were the leading cause of delay (risk level 14.31). Recommended measures include hiring staff appropriate to the project's size and scope, proper allocation of work, and ensuring inspections are conducted by qualified individuals. These findings can help stakeholders improve planning and risk management in future construction projects to mitigate delays.
References
W. Jiradamkerng, Construction Management, PathumThani: Wannakavee, 2013.
W. Onsrisombat, “The Study of Factors affected in building construction delays in northeastern region,” M.Eng. dissertation (Civil Engineering), Suranaree University of Technology, Bangkok, 2013.
A. Jitarree, “Problems and Solutions in project delay of large-scaled condominium buildings,” M.Eng. dissertation (Civil Engineering), Rangsit University, Bangkok, 2022.
P. Kullavanich, “Factors affecting delays in solar power company projects in Thailand,” M.B.A dissertation (Master of Business Administration M.B.A.), Thamasat University, Bangkok, 2018.
K. Kaewjindah, “Factors causing the delay of materials provision in interior office renovation project: case studies of high rise office buildings in Bangkok,” TDS dissertation (Architecture), Thamasat University, Bangkok, 2015.
W. Chantanasin, “Delay Protection and Remedy Guidelines for Condominium Construction: A Case Study of Condominiums in Bangkok,” TDS dissertation (Architecture), Thamasat University, Bangkok, 2010.
K. Padungkit. “Factors Affecting the Renovating Construction Delay in Terminal of Chiang Mai International Airport,” M.Eng. dissertation (Construction Engineering and Management), Chiang Mai University, Bangkok, 2019.
P. Thianphun and A. Prasittsom, “Delays factors in the construction of irrigation structure, case study: construction project of irrigation building for regional irrigation office 9,” Kasem Bundit Engineering Journal, vol. 8, no. 2, pp. 266-285, May-Aug. 2018.
S. CHANA and D. RINCHUMPHU, “Construction delays analysis acase study of residential condominiums in Chiang Mai,” in the 25th National Convention on Civil Engineering, Chonburi, Thailand, Jul. 15-17, 2020 pp. 251-255.
A. PERASITH and T. WANNAWIT, “Causes of Delays In Government Construction Projects and Solutions,” in The 25th National Convention on Civil Engineering, Chonburi, Thailand, Jul. 15-17, 2020, pp. 211-218.
T. Akkachai and P. Aprichart, “Risk assessment in construction project under the control of local administrative organizations in pathio district in chumphon,” Kasem Bundit Engineering Journal, vol. 8, no. 2, pp. 227-247, MayAug. 2018.
K. Boonchan and D. Methakullachat, “The Factors affecting delays of construction projects: a case study of department of public works and town planning of Samut Sakhon province,” in The Proceedings of the 58th Annual Conference, Bangkok, Thailand, February 5-7, 2020, pp. 406-415.
S. Tonlo and N. Leungboontnak, “Problems, Factors and construction delays improvement in thai government’s project,” M.Eng. (Civil Engineering), Khon Kaen University, Khon Kaen, 2009.
C. Uengbovontrakool, “A Risk study of building construction projects from perspective of construction management,” M. Sc. (Construction Project Management), Silpakorn University, Nakhon Pathom, 2020.
V. Mangnormake, “Risk Identification and analysis of Airport construction project in Lao PDR case Study: Nongkhang Airport construction project,” KKU RESEARCH JOURNAL (GRADUATE STUDY), vol. 17, no. 4, pp. 36-48, Oct.-Dec, 2017.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 Faculty of Industrial Technology, Suan Sunandha Rajabhat University

This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.
บทความที่ได้รับการตีพิมพ์เป็นลิขสิทธิ์ของคณะเทคโนโลยีอุตสาหกรรม มหาวิทยาลัยราชภัฎสวนสุนันทา
ข้อความที่ปรากฏในบทความแต่ละเรื่องในวารสารวิชาการเล่มนี้เป็นความคิดเห็นส่วนตัวของผู้เขียนแต่ละท่านไม่เกี่ยวข้องกับมหาวิทยาลัยราชภัฎสวนสุนันทา และคณาจารย์ท่านอื่นๆในมหาวิทยาลัยฯ แต่อย่างใด ความรับผิดชอบองค์ประกอบทั้งหมดของบทความแต่ละเรื่องเป็นของผู้เขียนแต่ละท่าน หากมีความผิดพลาดใดๆ ผู้เขียนแต่ละท่านจะรับผิดชอบบทความของตนเองแต่ผู้เดียว