Analysis of the loss in the hydroelectric power plant of the Pelton Turbine Hydro-Power plant: A Case Study of Huay Lamphan Yai Dam, Sekong Province, Lao PDR
Keywords:
Huay Lamphan Yai Dam, Pelton Turbine, Medium-sized Hydro-power Plant, Power Loss, Power is losing at the water pipe system, Power is losing at the nozzle, Power is losing at the turbine bladeAbstract
This article was to study the power loss in the power plant system at Huay Lamphan Yai Dam. the dam was a medium-sized hydroelectric dam with the height level of 611.86 meters using the Pelton turbine and the electric generator with the maximum capacity of 88 megawatts. the dam has a total of two generators sets. For the experiment, the electric generator was started running one by one, there was found that the water flow rate at 9.00 cubic meters per second affected the maximum power loss in various parts. In addition, the experiments for the first and the second electric generator were the same results. There were shown that the power loss at the water pipe system was equal to 16.34%, the power loss at the nozzles was equal to 2.69%, the power loss at the turbine blades was equal to 16.91%, and the power other losses namely include dispersion losses in turbine tanks, Generator loss and shaft loss between generator and turbine were equal to 64.11%, Moreover, for the experiment, both electric generators were started running together. There was found that the water flow rate at 18.00 cubic meters per second affected the maximum power loss in various parts of both generators. There were shown that the power loss at the water pipe system was 19.69%, the power loss at the nozzles was 2.60%, the power loss at the turbine blades was 16.34%, and the power other losses namely include dispersion losses in turbine tanks. Generator loss and shaft loss between generator and turbine were equal to 61.40%.
References
S. Vankham, “Study Of Efficiencies And Losses In The Operation Of Nam Dong Hydro Power Plant And Nam Ko Hydro Power Plant,” Of Engineering In Mechanical Engineering GRADUATE School Khon Kaen University, pp. 1-94, 2008.
S. Khamfaeng, P. Jittakorn and S. Sopapol, “Potential Development of Hydropower Dams in the Southern Region of Laos that Affects the Quality of Life of People in the Area Sustainably,” Burapha Journal of Political Economy, Vol. 7 No. 1, pp.5, 2019.
A. Khemphone, “Laos And International AID: The Role Of The World Bank On Namtheun 2 Hydro Electric Dam ProJect,” of Arts Program in International Relations Department of International Relations Faculty of Political Science Chulalongkorn University Academic, pp. 2, 2007.
N. Khot & H. Nikorn, “An Assessment of Electricity Generation Efficiency of the Pelton Turbine Hydro-Powerplant: A Case Study of Huay Lamphan Yai Dam, Sekong Province, Lao PDR,” in 12th Symposium of Graduate Studies, Graduate School Ubon Ratchathani Rajabhat University, Thai, 15 March 2020, pp. 834-835.
W. Bing, N. Ioan, M. Tad, M. Yi,. “Efficiency assessment of hydroelectric power plants in Canada: A multi criteria decision making approach” Energy Economics, vol.46, pp. 102-121, September. 2014.
Arne Kjølle, “HYDROPOWER IN NORWAY,” Norwegian University of Science and Technology Trondheim, CHAPTER 2, pp. 2.1, 2001.
Mishaal A Abdulkareem, “Hydro‐Water Power Plant,” CHAPTER (7), pp. 685, 2017.
Downloads
Published
How to Cite
Issue
Section
License
บทความที่ได้รับการตีพิมพ์เป็นลิขสิทธิ์ของคณะเทคโนโลยีอุตสาหกรรม มหาวิทยาลัยราชภัฎสวนสุนันทา
ข้อความที่ปรากฏในบทความแต่ละเรื่องในวารสารวิชาการเล่มนี้เป็นความคิดเห็นส่วนตัวของผู้เขียนแต่ละท่านไม่เกี่ยวข้องกับมหาวิทยาลัยราชภัฎสวนสุนันทา และคณาจารย์ท่านอื่นๆในมหาวิทยาลัยฯ แต่อย่างใด ความรับผิดชอบองค์ประกอบทั้งหมดของบทความแต่ละเรื่องเป็นของผู้เขียนแต่ละท่าน หากมีความผิดพลาดใดๆ ผู้เขียนแต่ละท่านจะรับผิดชอบบทความของตนเองแต่ผู้เดียว