Feasibility study of VLH hydro turbine installation at Nam Pung hydropower plant, Thailand

Main Article Content

Weerapon Nuantong
Sirivit Taechajedcadarungsri
Narong Khampool

Abstract

The aim of this research was to study the feasibility of installing a very low head (VLH) hydro turbine downstream of the  Nam Pung hydropower plant thereby increasing the potential of renewable energy resources of the Electricity Generating Authority of Thailand (EGAT). The water head level was limited to less than 2 meters and the flow rate to below 5 m3/ s due to site constraints. The selected hydro turbine was an axial flow turbine with an efficiency of 86.4%. The power output was 84.61 kW. Investment analysis was subsequently applied to estimate feasibility of the project. Analyses of results showed that the project is worthwhile in terms of investment. The payback period of actual price was 0.83 and 0.88 years and for the general price, it was 3.68 and 4.04 years, with annual interest rates of 6.75% and 12.625% respectively. The projected project lifespan is 25 years.

Article Details

How to Cite
Nuantong, W., Taechajedcadarungsri, S., & Khampool, N. (2016). Feasibility study of VLH hydro turbine installation at Nam Pung hydropower plant, Thailand. Engineering and Applied Science Research, 43(4), 210–214. Retrieved from https://ph01.tci-thaijo.org/index.php/easr/article/view/58715
Section
ORIGINAL RESEARCH

References

M. Ramos H, Simão M, Borga A. Experiments and CFD analyses for a new reaction microhydro propeller with five blades. J Energ Eng. 2013;139:109-17.

M. Ramos H, Simão M, N. Kenov K. Low-head energy conversion: A conceptual design and laboratory investigation of a microtubular hydro propeller. Mech Eng. 2012;2012:1-10.

Muis A, Sutikno P. Design and simulation of very low head axial hydraulic turbine with variation of swirl velocity criterion. Int J Fluid Mach Syst. 2014;7:68-79.

Sangal S, Garg A, Kumar D. Review of optimal selection of turbines for hydroelectric projects. Int J of Emerg Tech Adv Eng. 2013;3:424-30.

Sutikno P, K. Adam I. Design, simulation and experimental of the very low head turbine with minimum pressure and free vortex criterions. Int J Mech Mechatron Eng. 2011;11:9-16.

Adhikari P, Budhathoki U, R. Timilsina S, Manandhar S, R. Bajracharya T. A study on developing pico propeller turbine for low head micro hydropower plants in Nepal. J Inst Eng. 2013;9:36-53.

M. Ramos H, Borga A, Simão M. New design solutions for low-power energy production in water pipe systems. Water Sci Eng. 2009;2:69-84.

Forouzbakhsh F, Hosseini SMH, Vakilian M. An approach to the investment analysis of small and medium hydro-power plants. Energ Pol. 2007; 35:1013-24.

Ilak P, Krajcar S. Assessment of investment in small hydropower plants. Energ Environ Res. 2013;3:33-44.

Singal SK, Saini RP, Raghuvanshi CS. Optimization of low-head, dam-toe, small hydropower projects. J Renew Sustain Energ. 2010;2(4):1-13.

Elbatran AH, Yaakob OB, M. Ahmed Y, Shabara HM. Operation, performance and economic analysis of low head micro-hydropower turbines for rural and remote areas: A review. Renew Sustain Energ Rev. 2015; 43:40-50.

Wei Y, YuLin W, ShuHong L. An optimization method on runner blades in bulb turbine based on CFD analysis. Sci China Technol Sci. 2011;54:338-44.

Yang C, Zheng Y, Zhou D, Ge X, Li L. Bidirectional power performance of a tidal unit with unilateral and double guide vanes. Adv Mech Eng. 2013;2013:1-11.

Ge X, Feng Y, Zhou Y, Zheng Y, and Yang C. Optimization study of shaft tubular turbine in a bidirectional tidal power station. Adv Mech Eng. 2013;2013:1-9.

Rampano B. Water control structures: Designs for natural resource management on coastal floodplains. Sydney: NSW Department of Industry and Investment; 2009.

Lautier P, O’Neil C, Deschenes C, Ndjana HJN, Fraser R, Leclerc M. Variable speed operation of a new very low head hydro turbine with low environmental impact. Proceeding in Electrical Power Conference; 2007 Oct 25-26; Montreal: Canada. Montreal: IEEE; 2007. p. 85-90.

Electricity Generating Authority of Thailand. Wholesale tariff for MEA and PEA. Bangkok: EGAT; 2011.

Bulgaria–Serbia IPA Cross-border Programme. Comparative study of small hydropower stations. Bulgaria: Bulgaria–Serbia IPA; 2011.

Pasalli YR, Rehiara AB. Design Planning of Micro-hydro Power Plant in Hink River. Procedia Environmental Sciences 2014;20:55-63.