An integrated model of preventive maintenance and safety stock for a used production unit under leasing

Main Article Content

Thanawath Niyamosoth
Kazuho Yoshimoto
Shunichi Ohmori
Panitas Sureeyatanapas
Sirawadee Arunyanart

Abstract

In this paper, we propose an integrated model of preventive maintenance (PM) and safety stock for an unreliable production unit, subject to random failures, acquired by leasing. Maintenance activities, both preventive and corrective, are performed by the lessor under the lease contract, incurring maintenance costs to the lessor. The leased production unit is used by the lessee to produce parts for the subsequent production stage. To prevent the subsequent production stage from being interrupted during breakdowns and PM, the lessee must produce a certain amount of safety stock, incurring inventory costs to the lessee. Unlike other models in the literature that implicitly assume that the leased production unit is a new item, in this paper, we investigate the case where the leased production unit is one that has already been used. In this case, the lessor can perform reconditioning, prior to leasing, on the production unit being leased incurring a reconditioning cost to the lessor. A mathematical model is developed to determine the optimal PM cycle duration, reconditioning level, and safety stock size to minimise the total expected cost to the lessor and the lessee combined over the leasing horizon. The numerical results show that calculating the optimal values of all three decision variables by considering the lessor and the lessee simultaneously yields a more satisfactory result, in terms of the total expected cost over the leasing horizon, than when the parties are considered individually. Some managerial insights useful to both the lessor and the lessee are provided in the sensitivity analysis section.

Article Details

How to Cite
Niyamosoth, T., Yoshimoto, K., Ohmori, S., Sureeyatanapas, P., & Arunyanart, S. (2021). An integrated model of preventive maintenance and safety stock for a used production unit under leasing. Engineering and Applied Science Research, 48(4), 456–465. Retrieved from https://ph01.tci-thaijo.org/index.php/easr/article/view/243175
Section
ORIGINAL RESEARCH

References

Blischke WR, Murthy DNP. Reliability. New York: John Wiley & Sons; 2000.

Cheung KL, Hausman WH. Joint determination of preventive maintenance and safety stocks in an unreliable production environment. Nav Res Logist. 1997;44:257-72.

Dohi T, Okamura H, Osaki S. Optimal control of preventive maintenance schedule and safety stocks in an unreliable manufacturing environment. Int J Prod Econ. 2001;74:147-55.

Chelbi A, Ait-Kadi D. Analysis of a production/inventory system with randomly failing production unit submitted to regular preventive maintenance. Eur J Oper Res. 2004;156:712-8.

Chelbi A, Rezg N. Analysis of a production/inventory system with randomly failing production unit subjected to a minimum required availability level. Int J Prod Econ. 2006;99:131-43.

Gharbi A, Kenne JP, Beit M. Optimal safety stocks and preventive maintenance periods in unreliable manufacturing systems. Int J Prod Econ. 2007;107:422-34.

Murino T, Romano E, Zoppoli P. Maintenance policies and buffer sizing: an optimization model. WSEAS Trans Bus Econ. 2009;6:21-30.

Chakraborty T, Giri BC. Joint determination of optimal safety stocks and production policy for an imperfect production system. Appl Math Model. 2012;36:712-22.

Gan S, Zhang Z, Zhou Y, Shi J. Joint optimization of maintenance, buffer, and spare parts for a production system. Appl Math Model. 2015;39:6032-42.

Cheng GQ, Zhou BH, Li L. Joint optimisation of buffer size and preventive maintenance for a deteriorating upstream machine. Int J Syst Sci Oper Logist. 2015;2:199-210.

Zhou B, Liu Z. Optimizing preventive maintenance: a deteriorating system with buffers. Ind Manag Data Syst. 2016;116:1719-40.

Nahas N. Buffer allocation and preventive maintenance optimization in unreliable production lines. J Intell Manuf. 2017;28:85-93.

Lopes R. Integrated model of quality inspection, preventive maintenance and buffer stock in an imperfect production system. Comput Ind Eng. 2018;126:650-6.

Deiranlou M, Dehghanian F, Pirayesh MA. The simultaneous effect of holding safety stock and purchasing policies on the economic production quantity model subject to random machine breakdown. Int J Eng. 2019;32:1643-55.

Schutz J, Rezg N. Maintenance strategy for leased equipment. Comput Ind Eng. 2013;66:593-600.

Jaturonnatee J, Murthy DNP, Boondiskulchok R. Optimal preventive maintenance of leased equipment with corrective minimal repairs. Eur J Oper Res. 2006;174:201-15.

Hajej Z, Rezg N, Gharbi A. Integrated maintenance policy optimization under lease/warranty contract. Proceedings of the 13th International Conference on Industrial Engineering; 2013 Oct 21-23; Dubai, UAE.

Hajej Z, Rezg N, Gharbi A. A decision optimization model for leased manufacturing equipment with warranty under forecasting production/maintenance problem. Math Probl Eng. 2015:1-14.

Askri T, Hajej Z, Rezg N. Optimal integrated maintenance strategy for parallel leased machines with warranty periods. Proceedings of the 3rd Conference on Control and Fault-Tolerant Systems; 2016 Sep 7-9; Barcelona, Spain.

Hajej Z, Rezg N, Ali G. An optimal production/maintenance strategy under lease contract with warranty periods. J Qual Mainten Eng. 2016;22:35-50.

Askri T, Hajej Z, Rezg N. Jointly production and correlated maintenance optimization for parallel leased machines. Appl Sci. 2017;7(5):1-20.

Hajej Z, Rezg N, Askri T. Joint optimization of capacity, production and maintenance planning of leased machines. J Intell Manuf. 2020;31:351-74.

Niyamosoth T, Pathumnakul S. Joint determination of preventive maintenance and buffer stock for a production unit under lease. J Ind Eng Manag. 2018;11:497-512.

Pongpech J, Murthy DNP, Boondiskulchock R. Maintenance strategies for used equipment under lease. J Qual Mainten. 2006;12:52-67.

Ebeling CE. An introduction to reliability and maintainability engineering. 2nd ed. Illinois: Waveland Press; 2010.

Nandal N, Malik SC. On use of gamma distribution for evaluation of reliability and availability of a single unit system subject to arrival time of the server. J Reliab Stat Stud. 2019;12:93-102.