Conversion Challenges: A Case Study of Converting a Post and Lintel Structure to a Precast Concrete Structure Using Building Information Modeling (BIM)

Main Article Content

Chavanont Khosakitchalert
Nobuyoshi Yabuki

Abstract

Building Information Modeling (BIM) is now a widely accepted tool in the construction industry for designing and managing construction projects. However, converting a BIM model from one type of structure to another can be challenging. This case report aims to document the problems and challenges encountered when an engineer team attempted to create a precast concrete structural BIM model from an architectural BIM model that was initially designed to use a post and lintel system. The architect worked with the engineer team, facing several challenges when changing the structural system. One of the main challenges during the conversion process was redesigning structural elements as the structural behavior of the building changed significantly. The architectural layout and design of the building had to be altered to accommodate the new structural system. Additionally, the mechanical, electrical, and plumbing (MEP) systems had to be planned for installation within the precast concrete structure. These changes required significant effort and coordination between the different teams involved in the project. In conclusion, the case study demonstrates that converting a BIM model from one type of structure to another can be a challenging task that requires significant effort, coordination, and planning. It also shows that BIM models are not just a design tool but also a powerful tool for construction management and coordination.

Article Details

How to Cite
Khosakitchalert, C., & Yabuki, N. (2023). Conversion Challenges: A Case Study of Converting a Post and Lintel Structure to a Precast Concrete Structure Using Building Information Modeling (BIM) . Nakhara : Journal of Environmental Design and Planning, 22(3), Article 316. https://doi.org/10.54028/NJ202322316
Section
Research Articles

References

Allplan. (2023). Allplan precast - precast detailing. https://www.allplan.com/products/allplan-precast/

Collins, J. (2016). Incorporating BIM into architectural precast concrete fabrication. The 33rd International Symposium on Automation and Robotics in Construction (ISARC 2016), 392–402. https://doi.org/10.22260/isarc2016/0048

Elliott, K. S. (2019). Precast concrete structures (2nd ed.). CRC Press.

Gibb, A. G. F., & Isack, F. (2003). Re-engineering through pre-assembly: Client expectations and drivers. Building Research and Information, 31(2), 146–160. https://doi.org/10.1080/09613210302000

International Organization of Standardization. (2018). ISO 19650-1:2018 Organization and digitization of information about buildings and civil engineering works, including building information modelling (BIM) — Information management using building information modelling — Part 1: Concepts and principles. https://www.iso.org/standard/68078.html

Jang, S., & Lee, G. (2018). Process, productivity, and economic analyses of BIM–based multi-trade prefabrication—A case study. Automation in Construction, 89, 86–98. https://doi.org/10.1016/J.AUTCON.2017.12.035

Lee, J., Park, Y. J., Choi, C. H., & Han, C. H. (2017). BIM-assisted labor productivity measurement method for structural formwork. Automation in Construction, 84, 121–132. https://doi.org/10.1016/j.autcon.2017.08.009

Liu, Z., Lu, Y., Nath, T., Wang, Q., Tiong, R. L. K., & Peh, L. L. C. (2022). Critical success factors for BIM adoption during construction phase: a Singapore case study. Engineering, Construction and Architectural Management, 29(9), 3267–3287. https://doi.org/10.1108/ECAM-12-2020-1072/FULL/PDF

National Institute of Building Sciences. (2007). United States national building information modeling standard version 1 - part 1: overview, principles, and methodologies. Wordpress. https://buildinginformationmanagement.files.wordpress.com/2011/06/nbimsv1_p1.pdf

Priya, P. K., & Neamitha, M. (2018). A review on precast concrete. International Research Journal of Engineering and Technology, 5(1), 967–971. https://www.irjet.net/archives/V5/i1/IRJET-V5I1204.pdf

Sacks, R., Eastman, C. M., Lee, G., & Teicholz, P. M. (2018). BIM handbook: A guide to building information modeling for owners, designers, engineers, contractors, and facility managers (3rd ed.). Wiley.

Seadon, J., & Tookey, J. E. (2019). Drivers for construction productivity. Engineering, Construction and Architectural Management, 26(6), 945–961. https://doi.org/10.1108/ECAM-05-2016-0127

Sparkman, G., Gibb, A., & Neale, R. (1999). Standardisation and pre-assembly: Adding value to construction projects. Construction Industry Research and Information Association. https://books.google.co.th/books?id=fvm2AAAACAAJ

Takim, R., Harris, M., & Nawawi, A. H. (2013). Building information modeling (BIM): A new paradigm for quality of life within architectural, engineering and construction (AEC) industry. Procedia - Social and Behavioral Sciences, 101, 23–32. https://doi.org/10.1016/j.sbspro.2013.07.175

Underwood, J., & Isikdag, U. (2009). Handbook of research on building information modeling and construction informatics: concepts and technologies (1st ed.). Information Science Reference.

Wasim, M., & Oliveira, O. (2022). Efficient design of a prefabricated steel structure integrating design for manufacture and assembly concepts. Https://Doi.Org/10.1080/13287982.2022.2092949, 23(4), 356–369. https://doi.org/10.1080/13287982.2022.2092949

Wong, A. K. D., Wong, F. K. W., & Nadeem, A. (2009). Comparative roles of major stakeholders for the implementation of BIM in various countries. In H. Wamelink, M. Prins, and R. Geraedts (Eds.), Proceedings of the International Conference on Changing Roles: New Roles, New Challenges. https://www.researchgate.net/publication/228743459_Comparative_Roles_of_Major_Stakeholders_for_the_Implementation_of_BIM_in_Various_Countries

Zhang, L., Wen, M., & Ashuri, B. (2017). BIM Log mining: Measuring design productivity. Journal of Computing in Civil Engineering, 32(1), Ariticle 04017071. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000721