Bidirectional Tests on Two Shaft-Grouted Barrette Piles in Mekong Delta, Vietnam

Main Article Content

H. M. Nguyen
B. H. Fellenius
A. J. Puppala
P. Aravind
Q. T. Tran

Abstract

The piled foundation design of the 40-storey Exim Bank Building in Ho Chi Minh City, Vietnam, included bidirectional static loading tests on two shaft-grouted barrette piles tested in September 2013. The soil profile consisted of organic soft clay on silty sand with some gravel and silty clay. The cross-section area of the barrette piles, TP1 and TP2, was 2,800 mm by 800 mm. They were excavated to 65-m and 85-m depth, respectively, using grab-bucket excavation techniques with bentonite slurry and guide wall advanced ahead of the hole. For each pile, the bidirectional cell assembly was installed 16 m above the pile toe level and the reinforcing cage was instrumented with diametrically opposed vibrating wire strain-gages at three levels below and five (TP1) to eight (TP2) levels above the cell level. Shaft grouting was carried out along a 40-m length above the TP1 pile toe and along a 20-m length above the TP2 pile toe. The static loading tests were performed 23 and 25 days, respectively, after the piles had been concreted. Analysis of strain-gage records indicated Young’s modulus values of about 27 GPa on the nominal cross section of the piles. Simulation of the measured load-movement response indicated that the shaft resistance response was hyperbolic. The test schedule was interrupted by unloading/reloading cycles, which disturbed the gage data and included uneven load-holding durations which exacerbated the analysis difficulty.

Article Details

How to Cite
H. M. Nguyen, B. H. Fellenius, A. J. Puppala, P. Aravind, & Q. T. Tran. (2024). Bidirectional Tests on Two Shaft-Grouted Barrette Piles in Mekong Delta, Vietnam. Geotechnical Engineering Journal of the SEAGS & AGSSEA, 47(1), 15–25. https://doi.org/10.14456/seagj.2016.54
Section
Research Papers